OVERVIEW OF CC ADJUSTMENTS, MARKUPS, ASSIGNMENTS, AND OVERHEADS
There is a link at the end of this Topic to a step by step example for each of the principles detailed in this Topic.
GENERALLY
EstimatorVJ provides four basic operations (ignoring Vetting adjustments - described in a separate Topic) which can be used to manipulate the costs printed in Reports without altering the prime entries in the Estimate used to generate the final project cost.
These operations are CC Adjustments, Markup, Assignments, and Overhead Spread.
They are only executed when a report is Printed/Previewed with the option “Include Markups” selected, and they only affect the contents of the report, not the estimate itself. After running the report, all of the user’s calculations to build up the estimate are unchanged.
In arithmetic terms, the BID price results from the following formula applied to each item:
Generally
EstimatorVJ provides for a Markup percentage to be set to factor the estimated cost to a higher/lower value to cover costs other than profit and non-project overheads, and a Rounding adjustment (explained later).
(Estimated Cost) + CCAdjustment + (Estimated Cost) * (1.0 + (Markup %)/100.0)) + Rounding => Adjusted Cost
This Markup percentage can be set at the Estimate Section level, or at the Bill Item level.
Markup at Section LevelEstimatorVJ provides mechanisms for re-assigning costs from one place in the estimate to another, without corrupting the source estimate, so that the re-assignment can always be reviewed or reversed if desired.
The re-assignment mechanism moves costs from one or more cost items to one or more cost items, following suitable rules. This allows a user to create a detailed estimate measured and priced not necessarily in the order dictated by the Client's Schedule, then assign (move) the estimated costs to the appropriate Client Schedule items.
The items being re-assigned are termed the 'source' items, and the items receiving the re-assignment are termed the 'destination' items.
NOTE:
Overhead and Markup is applied at the source and destination items and
is NOW maintained during the transfer process.
Be aware if estimating with multiple currencies, as assignments in the base currency is not currently supported, and will be made in and appear as the bid currency values.
Assignments
can be made in Section, Cost, or Rate workup sheets, and are entered
into the column registered as the 'Assign' column (by default
'ASSIGN'). The currently registered 'Assign' column is specified in
the Project's MORE defaults section.
Overhead spread
is a method of dispersing Indirect Job Costs (e.g. Preliminaries, Site
Staff, Escalation, Mobilisation, Demobilisation, Recurring Overheads,
etc) to Direct Job Costs (typically items that are to be reported with a
BID value to the client), and in essence is a SPECIAL TYPE OF ASSIGNMENT
having it's own column called 'OH' where the source
and destination items are flagged.
The source items are
those items that have an '=' character entered into the OH column
adjacent to the appropriate cost item. Destination items are those items
that either do not have an entry in the OH column, or have a weighting
(*+-%#) factor in the OH column.
The particular weighting of '*0' means this item will not receive Overhead spread - used, for example, in Prime Cost items.
Direct amounts can be added/subtracted by placing the amount in the OH columne.g '+1000' placed in the OH column would add 1,000 to this item from the pool, whereas '-1000' would subtract 1,000 from this item and add this to the pool.
A special flag '#nnnn' can be used in the OH column. If entered, then the OH amount will be equal to 'nnnn'-AdjustedCost, thus making the BID amount for this item = 'nnnn'. The resultant adjustment is then added/subtracted to the general OH Spread for distribution to the remaining items in the Estimate.
A special flag '%nnnn' can be used in the OH column. If entered, then the OH amount will be equal to 'nnnn'/100*AdjustedCost. The resultant adjustment is then added/subtracted to the general OH Spread for distribution to the remaining items in the Estimate.
At the appropriate time, the program then aggregates the cost of all items designated as overhead (=), and spreads this cost to all items in the Estimate, pro-rata based upon each item's adjusted cost (ADJCOST).
Distributing Overhead according to 'CC'
In normal cases, Overhead is distributed according to each item's ADJUSTED COST, however it has become more prevalent now for Tender Submissions to require the Schedule of Priced Items to be submitted in accordance with a Client's 'CC' Breakdown (e.g. LA, MA, PL). In such cases, there has been a requirement for Tenderers to nominate how much of the General Overhead Distribution is to be applied to each of these Client defined 'CC' groups.
EstimatorVJ
accommodates this by means of a setting in the Project's 'MORE'
definitions section. Here there are buttons called 'Use CC
Distributions' and 'pro-rata to CC's'. When one or both of these are
ticked overhead spread gets distributed in one of two ways according to
Cost Categories
If BOTH the 'Use CC Distributions' and 'pro-rata to CC's' buttons are Ticked:
The Overhead Spread is distributed over all destination items with a CC equal to one of those that have been selected by placing a tick in the corresponding 'Include OH' check boxes.
In
the above example, ALL Overhead will get distributed pro-rata to the
'adjusted cost of MA' in the target items.
If only the 'Use CC Distributions' button is Ticked:
How much is distributed to each 'CC' of the destination items is controlled by the 'CC' making up the source item's cost. If the source of Overhead Spread is "MA", then this source's cost will be spread over the Adjusted Cost of destination items with a CC of "MA".
Accordingly,
you can also determine what proportions of the source item is spread to
which CC of the destination items.
The following example illustrates one way of achieving this:
The source item for distribution totalling $120,000 will be distributed in the ratio of 50% to Labour, 40% to Material, and 10% to Plant. NOTE that the COST to be distributed in actual fact is the QTY of the parent. In this manner, the COST can be built up in a Quantity Workup Sheet, whereas the distribution ratio can be controlled in the Rate workup sheet.
Considerations1. Use of the special flags '*+-#' is supported at the destinations
2. There must be a cost for each 'CC' to receive 'CC' overhead distributions. If not, then a message similar to the following will be given:
The user can develop two estimates for the same task or group of bill items, review them one against the other, then decide to omit one alternative from the estimate.
This is done by inserting a 0 (zero) in the F column on the same row as the Unit of each bill item which is to be omitted.
As each zero is entered, estimator changes the cost and rate to nil for that item. Where a workup sheet exists for the item, zeros are automatically entered into the F column of the workup sheet opposite each resource.
The estimated costs are ignored when the Item Cost totals are computed for that estimate section. When a resource usage report is run, the resources in the workup sheet for the omitted item will not be counted.
The omission can be reversed by deleting the zero at the bill item level. The software will remove the corresponding zeros from the workup sheet, and redisplay the Item Cost.
If the omission is to be reversed, always make the deletion at the bill item level. If the zeros at the workup sheet level are individually deleted by the user, the zero at the bill item level will remain, and on the next re-rate, the item will again be reset to nil
The omit flag 0 can also be entered at the resource level in a bill item cost or rate workup sheet. Enter the zero into the F column of the workup sheet, and the Item Cost for that resource row will be changed to nil. The user can thus omit the Item Cost for one or two resources while retaining others on the workup sheet.
Click here for a step by step illustration of each of the above principles.