EstimatorVJ


The Vetting System


Generally


The Vetting System in EstimatorVJ allows you to code the Client Schedule of items in the estimate with a coding system such that a Subcontract Bill of Quantities can be produced for each Subcontract. Vetting at the RESOURCE level can also be done.


These Bills/Resource Lists can then be priced by the various Subcontractors, then entered into the Vetting System, either as a lump sum or individually priced items, then a Subcontract Comparison made to ascertain the best Subcontract quote.


The accepted Subcontractors are then registered in the System. Tender reports can be flagged to use the Accepted Subcontractors quotations in lieu of or in addition to your prices when printing the Tender price. 


The PROCEDURE


Listed below in point form are the general steps involved in managing a Project requiring Subcontract quotations for all or part of the project.

The method of carrying out each step is detailed under 'The METHOD' later.


1.    Create the Project


The project must be created using the  Default Template 'Vetting'..

This Project ensures you have the KEY columns, in particular BQREF asnd SCDE, necessary in each of the worksheets for the Vetting to work.


2.    Enter the Client Schedule/ Bill of Quantities


This can be done by either typing in the Client Schedule or importing electronically.


3.    Uniquely Identify Each Item with a BQREF.


Every item in the Client Schedule must have a unique BQREF. This is the key link between the items in your Client Schedule and the Vetting system items.


There is a facility to 'Autonumber' all items in the Project under the 'Section->Autonumber' option in the Project Window.


4. Enter the list of Subcontracts (Register)


Select the option 'Vetting->S/C List' and enter the list of Subcontracts.

Additional Subcontracts can be added later as needed.


This list comprises two columns of information; the  ‘Subcontract code' (SCDE column), and the 'Subcontract Name’.


e.g DEM Demolisher

COSU Concrete Supply

COPL Concrete Place


5.    Price and Code the Client Schedule


Each Bill item in each Section that is required to be quoted on, must be coded with a valid Subcontract code, as defined in the SCDE column of the 'List of Subcontracts' as mentioned in 4. above.


This code is entered in the SCDE column on the same line as the BQREF.


6.    Generate the Vetting Sheets


Once the SCDE codes have been entered for the desired Client Bill items, the Vetting sheets can be generated.


7.    Print a Subcontract Bill of Quantities


Open the Vetting Sheet for the Subcontract in question, print the Bill of Quantities, and send off to the appropriate Tenderers for pricing.


8.    Enter the Subcontract Quotations Received


As the quotations from the Subcontractors are received, enter these into the appropriate Vetting Sheet by either entering their rate or cost for each item, or entering their quotation as a Lump Sum. 


The Vetting Sheet by default has facility initially for four Subcontract quotes, however these can be expanded to up to 10 per sheet.


Facilities are available for:


9. Nominate which Subcontractor(s) is 'Accepted'


Select the items which you want to 'Accept' for each Subcontractor. You can accept all or some of a Subcontractor's quoted items, and you can accept items from more than 1 Subcontractor.


10. Finalize Each Subcontract


Before you can Transfer the Accepted Quotations back into the Estimate, each Subcontract Vetting Sheet has to be 'Finalized'.

This simply informs VJ that each Subcontract is FINAL and can be used to adjust the Estimated Costs.


NOTE: Whenever a change is made to the Estimate, ALL vetting sheets will be reset as 'Not Updated' and 'Not Finalized'.


11. Transfer the Subcontractor(s) 'Accepted' Quotes back into the Estimate


Once you have completed entering and accepting the appropriate quotations in all of the Vetting sheets and marked them as Finalized, you TRANSFER these accepted quotations back into the base Estimate.

Essentially, this process involves the program:

for Bill Items:

creating a 'VETADJ' column in each Estimate Section if it doesn't already exist, and then setting the 'adjustment value' against each vetted item such that the estimated 'COST' plus the 'VETADJ' equals the ACCEPTED value in the vetting sheet.

for Resource Items:

copying the EstRate (if present) to the Purch/P or Rate columns

creating the following columns in the Local Library if they don't already exist

EstRate

Subby

then

copying the Purch/P or Rate to the EstRate column

entering the Accepted Rate into the Purch/P or Rate columns

Recalculating the Project


12.    Print the Reports


There are two sets of Reports:

  1. Reports generated from the 'Vetting' TAB in the Project Print Options dialog
    These reports are specific Vetting type reports
  2. Reports from the 'General' TAB in the Project Print Options dialog
    These reports are the normal Reports which include an option to 'Include Vetted Costs'. This option then simply causes the program to replace your Estimate Cost for each item with the Accepted Subcontract quotations for that item


The METHOD


1.    Create the Project


Create the Project in the normal manner except choose the Template 'Vetting'.


It contains the necessary structure of the Section Worksheet, and Rate/Cost Workup sheets for Subcontract coding, and the Vetting sheet for collecting and maintaining the Items requiring quotations from the SUBCONTRACTORS.


2.    Enter the Client Schedule/ Bill of Quantities


This can be done by either typing in the Client Schedule or importing electronically.


3.    Uniquely Identify Each Item with a BQREF.


Every item in the Client Schedule must have a unique BQREF. This is the key link between the Bill Items in your Client Schedule and the Vetting system Bill Items.


There is a facility to 'Autonumber' all items in the Project under the 'Section->Autonumber' option in the Project Window.


4.    Enter the list of Subcontracts


Select the option 'Vetting->S/C List' and enter the list of Subcontracts.


This list comprises two columns of information; the  ‘Subcontract code' (SCDE column), and the 'Subcontract Name’.


e.g DEM Demolisher

COSU Concrete Supply

COPL Concrete Place


A vetting sheet for each of these codes will be created and named using this code, so once you have created a Vetting sheet, DO NOT DISASSOCIATE IT by changing the Subcontract Code (SCDE).


You can however change the 'Subcontract name' at any time.


5.    Price and Code the Client Schedule


Each Bill Item in each Section that is required to be quoted on, must be coded with a valid Subcontract code. These codes are those as defined in the SCDE column of the 'List of Subcontracts' as mentioned in 3. above.


These codes are entered in the SCDE column on the same line as the BQREF, 


If an item involves more than 1 Subcontract, then you can either:

NOTE: The validity of the SCDE codes entered at this stage will not be validated. This occurs when the Vetting Sheets are being 'generated' or 'updated'. 


6.    Generate the Vetting Sheets


Once the SCDE or Resource codes have been entered for the targetted Client Bill items, the Vetting sheets can be generated.


Generate the Vetting sheets manually by editing the Subcontract Vetting sheets of interest.

7.    Editing a Vetting Sheet


You edit a Vetting Sheet (you must have edited the 'Subcontract List' first as described in 4. above) by clicking the option 'Vetting->Edit', then double clicking the desired Subcontract from the list presented.


8.    Updating a Vetting Sheet


Edit the Vetting Sheet to be updated, and click the option 'Vetting->Update'.


VJ will now:

If a Bill Items vetting sheet:

If a Resource vetting sheet:

If we make changes to the Estimate Sections or their workup sheets at any time, all existing Vetting Sheets will have their 'status' changed to 'not updated', 'altered', and 'not Finalized'. The significance of this will be explained later.


9.    Print the Subcontract Bills of Quotations


When you are satisfied that a Subcontract's Vetting Sheet contains the appropriate items to be quoted, you can now 'print the Subcontract Bills of Quotations'.

  1. Click the 'Print' option in the Vetting TAB
  2. Click the 'Subcontract BQ's' option
  3. Select the Subcontracts to Print using the FROM and TO combo box lists
  4. Click 'Preview' or 'Print'


NOTE:

If the 'status' of any Subcontract is 'not updated', then it will not be printed and a warning given. You will then be required to edit the Subcontract(s) in question and execute the 'Update' option, review the results, and then execute the Print option again.

Remember, every time you alter any data in the base estimate the status for every Vetting Sheet is reset to 'not updated', 'altered', and 'not finalized'. 


10.    Enter the Subcontract Quotations Received


Generally


The Vetting Sheet by default has facility initially for four Subcontract quotes, however these can be expanded to up to 10 per sheet.


Initially these 10 Subcontractors are given the name 'Subby #n', where n=1 to 10. As subcontractors are invited to Tender, their details are registered to this sheet.


As the quotations from the Subcontractors are received, these are entered into the Vetting Sheet by either entering their rate or cost for each item, or entering their quotation as a Lump Sum and spreading it over the items they have quoted on.


Registering a Subcontractor


You register a Subcontractor to a Vetting Sheet by:


Entering a Subcontractor's Quotation - if supplied as Item Costs or Lump Sum Quotation


If the Subcontractor has supplied his quotation as Rates and/or Costs for each item, then


If the Subcontractor has provided a Lump Sum quotation only, then


If the Subcontractor has not priced all the items, then you will need to add in a price for these items using either


NOTE: The '%Discount' field entered in the Subcontractor's details (register) is only used in the case of a Lump Sum Quotation being used.


Entering a Subcontractor's Quotation as 'Estimated Costs'


In most circumstances, a Subcontractor's quotation will exclude certain items. As a fair and meaningful comparison between the various Subcontractor's quotes, all items need to be priced.


A formal way of achieving this is to 'TAG' the unpriced items with your Estimated Cost.


This is achieved by:

These 'TAG'ging processes provide a way for the program to automatically modify the quoted values when subsequent adjustments are made

e.g. Altering the Quotation for a Subby as a Lump Sum


Entering a Subcontractor's Quotation with another Subcontractors Quote


In most circumstances, a Subcontractor's quotation will exclude certain items. As a fair and meaningful comparison between the various Subcontractor's quotes, all items need to be priced.


Another formal way of achieving this is to 'TAG' the unpriced items with another Subcontractor's price.


This is achieved by:

These 'TAG'ging processes provide a way for the program to automatically modify the quoted values when subsequent adjustments are made

e.g. Altering the Quotation for a Subby as a Lump Sum


Selecting the Items to be TAGGED


As mentioned earlier, before you can REGISTER TAGS to an item, you must select the items to be TAGGED. This means selecting (ranging/highlighting) the cells IN THE COST column of the items to be TAGGED.


This can be done by either:

9. Nominate which Subcontractor(s) is 'Accepted'


Select the items which you want to 'Accept' from the desired Subcontractor - you can accept all or some of a Subcontractor's quoted items, and you can accept items from more than 1 Subcontractor.


Once the items have been selected, click the 'Mark as Accepted' button.


The program will then add the 'A' TAG to the end of any existing TAGs for the selected items, and update the values in the 'ACCEPTED' column. It is the value in the 'ACCEPTED' which will be used in the various TENDER reports in lieu of your Estimated cost.


10.    Transfer the 'Accepted' Quotations back to the Estimate


When you have finalized ALL Vetting Sheets with the ACCEPTED values, you MUST TRANSFER THE ACCEPTED VALUES BACK INTO THE ESTIMATE.


Click the 'Vetting->Transfer' button in the Project Window, and the program will:

10.    Print the Reports


There are two sets of Reports:

  1. Reports generated from the 'Vetting' TAB in the Project Print Options dialog
    These reports are specific Vetting type reports
  2. Reports from the 'General' TAB in the Project Print Options dialog
    These reports are the normal Reports which include an option to 'Include Vetted Costs'. This option then simply causes the program to use the VETAMT for that item in lieu of your estimated COST.

Do's and Dont's

  1. Don't
    Add columns to the Vetting Sheets (other than with the 'Add S/C button)
    Delete columns from the Vetting Sheets
    Rename or modify the Formula for any 'COSTn', 'RATEn', 'TAGn' columns.
    These columns are reserved for the proper functioning and maintenance of each Subcontract.
  2. Do
    Add additional Subcontractors using the 'Vetting->Add S/C' button. This guarantees the proper maintenance of the critical Subcontract columns and their functionality.

The TUTORIAL


Generally

The following is a TUTORIAL on how to get started using the VETTING System in EstimatorVJ. It is assumed that you already are experienced in constructing an Estimate in EstimatorVJ. If you are not, then you need to go through the standard Tutorial first, and become proficient in using EstimatorVJ.

We have provided a small Project to work with - 'A Vetting Example' - initialized with some data in the 'Concrete' section o illustrate the concepts and steps you will need to take to use the Vettting system properly.

This Tutorial will follow a step by step format, each step starting with the Theory, followed by the Practical instructions. The Practical instructions will be shown in a BOLD/ITALICIZED/UNDERLINED  font.

About the Project

The Project 'A Vetting Example' is provided with the Program and simply contains a few Insitu and Precast items in the 'Concrete' section.

These items are sufficient to demonstrate practically all of the concepts you will need to learn to accomplish a successful Tender submission on a Project which incorporates a mixture of items priced from first princoples (using Resources) and items priced from Subcontractor Quotations.


The Procedure

1.    Coding the Estimate with the Subcontract Codes

Open the Project 'A Vetting Example', then open the Estimate Section 'Concrete'.

The items in this Section were provided by the Quantity Surveyor.   

For this Tutorial, we will assume that we will be getting Subcontract Quotes for the INSITU and PRECAST items from different Subbies, so we will need to REGISTER these two Subcontracts. 

2.    Registering the Subcontracts

We do this by clicking the option "Vetting->S/C List"   , and then typing into the SCDE column a UNIQUE code, and the subcontract title  in the Subcontract Name column.

The two subcontracts have already been registered for you.

Press the 'ESC' key to close the S/C List (Registry), and return to the 'Concrete' section.

3. Preparing the Bill for Subcontract Coding

One condition that is absolute in a Vetted Project - every item that is to be vetted must have a BQREF unique to the Project.


e.g. if an item to be vetted has a BQREF of '1', then no other item in this Project, whether it be an item to be vetted or not, can also have a BQREF of '1'.

If the items are not already BQREF'd, then use the Autonumber function in EstimatorVJ to do so as follows:

Done!

4.    Subcontract Coding the Bill

We are now ready to specify the Subcontracts which apply to each item, and do this by placing in the SCDE column, the Subcontract code or codes (separated by a space) which represent the Subcontractor(s) who will be providing a quotation for each of the items.

If an item involves more than 1 Subcontract, then you can either:

The items in the CONCRETE Section have already been coded as an example.  Take notice especially the last item which has been multiple coded by creating a Rate Workup sheet and entering the Subcontracts required in there.

The next step in the Vetting process is to CREATE the Vetting Sheets for each of the Subcontracts. In this example, the  'Insitu' and 'Precast' Concrete.
  

5.    Creating the Vetting Sheets  

This step involves opening up each of the Subcontract Vetting sheets, initially blank, then populating them (Updating) with the appropriately coded items in the estimate .

6.    Print a Subcontract Bill of Quantities

This report can be sent off to each of the Subcontractors who have been invited to quote on each of the Subcontracts.


It lists out each of the items in the selected vetting sheets, with their BQREF, Description, Unit, and Quantity included, but no other information, so it can be printed at any time, even though other contractor's or your estimates have been entered.

Click the 'Vetting->Print' button in the Project Window, select the FROM and TO Subcontracts to be included, then click the 'Print' button.

7.    Entering a Subcontractor's Quotations as a Lump Sum

When we have Priced the Base Estimate

We are now going to edit the 'COINS' subcontract, and enter the FIRST subcontractor's quotation as a lump sum.
When the Base Estimate has not been priced

The above is the standard procedure when we have priced the items in the base Estimate, since when the update of the vetting sheet is activated, the items that come in will have their rates and costs carried in as well. Thus when we distribute the subcontractor's quote, there will be meaningful data to prorata with.

Let's now look at the example where we have predominantly NOT priced our base Estimate, but simply S/C coded our Bill of Quantities. This is useful in getting a Subcontract Bill of Quantities off to the Subcontractors as fast as possible to get keener quotations or in short Tender periods.

Essentially we start the process the same way:
    Select the Edit vetting sheet option
    Edit the S/C details

Since we are already in the Vetting Sheet we want to be in, we continue such by first cleaning up what we previously entered
We will now RATE the items while in this vetting sheet so as to form a basis for distributing Lump Sum Quotations from our Subcontractors The program will now add the tag 'Q1', and calculate and display the distribution accordingly.

   8.    Entering a Subcontractor's Quotations as Rated/Costed Items

Lets now look at the situation where the THIRD Subcontractor has supplied his quotation as a 'Rated Bill'.

If a subcontractor has not supplied a quotation for all of the items, we have the following alternatives for the unrated items
Let's apply each of these to the item CO/3 for subcontractor #2.
The principle purpose of these special TAG's is to provide a means for the program to adjust the Subcontractor rates and Costs should any of the details be amended or updated later.

9. Nominate which Subcontractor(s) is 'Accepted'

This aggregated 'Accepted' cost of each item  is used to 'adjust' the COST in the base estimate to reflect the subcontractor quotations. In other words, the program at the approriate moment, will add up all the subcontractor costs TAGGED as A(ccepted), and place the sum in the 'Accepted' column. The difference between the 'Accepted' and estimated 'Cost' is transferred back into the base estimate and placed in the 'VETADJ' column.

Consequently, it is MOST IMPORTANT to mark as 'Accepted' ALL the appropriate items. There are Reports you can print to highlight this, and will be discussed later.

In our example, let us assume we are going to ACCEPT the quotations provided by Subcontractor #2.

10.    Finalizing the Vetting Sheets

Various operations in the Vetted Project depend on the fact that all the Vetting Sheets must be 'Finalized' for the operation to complete
e.g.
Registering each of the Vetting Sheets as 'Finalized', is the way the program knows that you have completed and are satisfied with the data in each of the Vetting Sheets.

Some important concepts and considerations for you to know:
You mark the status of the vetting sheet as 'Finalized' by clicking the 'Finalize' button when it is RED. If the vetting sheet is 'up to date' (that is has been 'Updated' since the last alteration to any of the Estimate Sections), the finalized status will be set to 'true' (GREEN), if not then it will be set to 'false' (RED).

11.    Transferring the Accepted Quotations back into the Estimate

As discussed previously, when ALL vetting sheets have been marked as finalized, the program will transfer the 'Accepted' values in the vetting sheets back into the Estimate Sections and into the column 'VETADJ' adjacent to the pertinent BQREF item. The value it places in the VETADJ column will be the difference between the estimated cost and the accepted cost in the vetting sheet for that item.

This option is started by:

END OF TUTORIAL