EstimatorVJ
The Vetting System
Generally
The Vetting System in
EstimatorVJ allows you to code the Client Schedule of items in the
estimate with a coding system such that a Subcontract Bill of
Quantities can be produced for each Subcontract. Vetting at the
RESOURCE level can also be done.
These Bills/Resource Lists
can then be priced by the various Subcontractors, then entered
into the Vetting System, either as a lump sum or individually
priced items, then a Subcontract Comparison made to ascertain the
best Subcontract quote.
The accepted
Subcontractors are then registered in the System. Tender reports
can be flagged to use the Accepted Subcontractors quotations in
lieu of or in addition to your prices when printing the Tender
price.
The
PROCEDURE
Listed below in point form
are the general steps involved in managing a Project requiring
Subcontract quotations for all or part of the project.
The method of carrying out
each step is detailed under 'The METHOD' later.
1. Create the Project
The project must be
created using the Default Template 'Vetting'..
This Project ensures you
have the KEY columns, in particular BQREF asnd SCDE, necessary in
each of the worksheets for the Vetting to work.
2. Enter the Client Schedule/ Bill
of Quantities
This can be done by either
typing in the Client Schedule or importing electronically.
3.
Uniquely Identify Each Item with a BQREF.
Every item in the Client
Schedule must have a unique BQREF. This is the key link between
the items in your Client Schedule and the Vetting system items.
There is a facility to
'Autonumber' all items in the Project under the
'Section->Autonumber' option in the Project Window.
4. Enter the list of Subcontracts
(Register)
Select the option
'Vetting->S/C List' and enter the list of Subcontracts.
Additional Subcontracts
can be added later as needed.
This list comprises two
columns of information; the
‘Subcontract code' (SCDE column), and the 'Subcontract
Name’.
e.g DEM Demolisher
COSU Concrete
Supply
COPL Concrete
Place
5. Price and Code the Client
Schedule
Each Bill item in each
Section that is required to be
quoted on, must be coded with a valid Subcontract code,
as defined in the SCDE column of the 'List of Subcontracts' as
mentioned in 4. above.
This code is entered in
the SCDE column on the same line as the BQREF.
6.
Generate the Vetting Sheets
Once the SCDE codes have been entered for the
desired Client Bill items, the Vetting sheets can be generated.
7.
Print a Subcontract Bill of Quantities
Open the Vetting Sheet for
the Subcontract in question, print the Bill of Quantities, and
send off to the appropriate Tenderers for pricing.
8. Enter the Subcontract Quotations
Received
As the quotations from the
Subcontractors are received, enter these into the appropriate
Vetting Sheet by either entering their rate or cost for each item,
or entering their quotation as a Lump Sum.
The Vetting Sheet by
default has facility initially for four Subcontract quotes,
however these can be expanded to up to 10 per sheet.
Facilities are available
for:
- Spreading the Lump Sum quotation over a
selected group of items
- Setting the Cost of selected items
equal to the your Estimated Cost
- Setting the Cost of selected items to
equal another Subcontractors quote
9. Nominate which
Subcontractor(s) is 'Accepted'
Select the items which you
want to 'Accept' for each Subcontractor. You can accept
all or some of a Subcontractor's quoted items, and you can accept
items from more than 1 Subcontractor.
10. Finalize Each
Subcontract
Before you can Transfer
the Accepted Quotations back into the Estimate, each Subcontract
Vetting Sheet has to be 'Finalized'.
This simply informs VJ
that each Subcontract is FINAL and can be used to adjust the
Estimated Costs.
NOTE:
Whenever a change is made to the Estimate, ALL vetting sheets
will be reset as 'Not Updated' and 'Not Finalized'.
11. Transfer
the Subcontractor(s) 'Accepted' Quotes back into the
Estimate
Once you have completed
entering and accepting the appropriate quotations in all of the
Vetting sheets and marked them as Finalized, you TRANSFER these
accepted quotations back into the base Estimate.
Essentially, this process
involves the program:
for
Bill Items:
creating
a 'VETADJ' column in each Estimate Section if it doesn't already
exist, and then setting the 'adjustment value' against each vetted
item such that the estimated 'COST' plus the 'VETADJ' equals the
ACCEPTED value in the vetting sheet.
for
Resource Items:
copying
the EstRate (if present) to the Purch/P or Rate columns
creating
the following columns in the Local Library if they don't already
exist
EstRate
Subby
then
copying
the Purch/P or Rate to the EstRate column
entering
the Accepted Rate into the Purch/P or Rate columns
Recalculating
the Project
12.
Print the Reports
There are two sets of
Reports:
- Reports generated from the 'Vetting'
TAB in the Project Print Options dialog
These reports are specific Vetting type reports
- Reports from the 'General' TAB in the
Project Print Options dialog
These reports are the normal Reports which include an option to
'Include Vetted Costs'. This option then simply causes the
program to replace your Estimate Cost for each item with the Accepted
Subcontract quotations for that item
The
METHOD
1.
Create the Project
Create the Project in the
normal manner except choose the Template 'Vetting'.
It contains the necessary
structure of the Section Worksheet, and Rate/Cost Workup sheets
for Subcontract coding, and the Vetting sheet for collecting and
maintaining the Items requiring quotations from the
SUBCONTRACTORS.
2.
Enter the Client Schedule/ Bill of Quantities
This can be done by either
typing in the Client Schedule or importing electronically.
3.
Uniquely Identify Each Item with a BQREF.
Every item in the Client
Schedule must have a unique BQREF. This is the key link between
the Bill Items in your Client Schedule and the Vetting system Bill
Items.
There is a facility to
'Autonumber' all items in the Project under the
'Section->Autonumber' option in the Project Window.
4.
Enter the list of Subcontracts
Select the option
'Vetting->S/C List' and enter the list of Subcontracts.
This list comprises two
columns of information; the
‘Subcontract code' (SCDE column), and the 'Subcontract
Name’.
e.g DEM Demolisher
COSU Concrete
Supply
COPL Concrete
Place
A vetting sheet for each of these codes will be
created and named using this code, so once you have
created a Vetting sheet, DO NOT DISASSOCIATE IT by
changing the Subcontract Code (SCDE).
You can however change the
'Subcontract name' at any time.
5. Price and Code the Client
Schedule
Each Bill Item in each
Section that is required to be quoted on, must be coded with a valid
Subcontract code. These codes are those as defined in the SCDE
column of the 'List of Subcontracts' as mentioned in 3. above.
These codes are entered in
the SCDE column on the same line as the BQREF,
If an item involves more
than 1 Subcontract, then you can either:
- Create a Rate or Cost workup sheet
- do
not code SCDE the line containing the workup sheet as if you
do it will ignore the workup sheet details and use that code
instead
- enter
an item for each Subcontract required, specifying a valid SCDE
code in the SCDE column. A BQREF is not required at this
level, as this is specified at the Estimate Section worksheet
level
- you can, but it is not
mandatory, enter your estimate of cost for that
Subcontract for this item
- an entry will be added to the
corresponding Vetting Sheet for each item
- Enter the multiple SCDE codes, one for
each Subcontract and separated by the SPACE character
- e.g. 'COSU COPL REFR'
- an entry will be added to
each Vetting Sheet for each SCDE code
- the COST amount in the
Vetting Sheet will be the COST of this client item divided by
the number of codes
NOTE: The validity
of the SCDE codes entered at this stage will not be validated.
This occurs when the Vetting Sheets are being 'generated' or
'updated'.
6.
Generate the Vetting Sheets
Once the SCDE or Resource
codes have been
entered for the targetted Client Bill items, the Vetting sheets
can be generated.
Generate the Vetting
sheets manually by editing the Subcontract Vetting sheets of
interest.
- Click the
'Vetting->Edit VS' option while in the Estimate Section
OR
Click the 'Vetting->Edit' options while at the Project
Window
- Select the
Sheet to edit from the list
Initially this sheet will be blank, and will default to
Vetting Bill Items as depicted below

If this sheet is for Vetting Bill Items then move to the next
step : "Update"
If this sheet is for Vetting Resources:
- click the 'RC' radio button just under the "VS Type" label
and the sheet will adjust accordingly as depicted below:

- NOTE the different column headings
- Now open the Left Panel and select the "RCList" TAB exposing
all the Resources for this project

- Select the first Resource to be included in this Subcontract
and press ENTER
The Resource will be added to the Vetting Sheet
- Move to the next Resource required and press ENTER and it
will also be added
- Repeat this process until all resources required have been
added
- Now click
the 'Update' button
If this is a Resource Vetting Sheet
- a list of all resources used in the project together with
their aggregated quantities is generated
- the quantity for each resource in this sheet is then
updated from this list
If this is a Bill Item vetting sheet:
- The program creates a list of all items in the
Estimate with this sheets matching SCDE code, and imports
this list into this worksheet
e.g.

7. Editing a Vetting Sheet
You edit a Vetting Sheet
(you must have edited the 'Subcontract List' first as described in
4. above) by clicking the option 'Vetting->Edit', then double
clicking the desired Subcontract from the list presented.
8.
Updating a Vetting Sheet
Edit the Vetting Sheet to
be updated, and click the option 'Vetting->Update'.
VJ will now:
If a
Bill Items vetting sheet:
- Set the flag in the 'Status'
column for each line 'O' (Original)
- browse each Estimate Section
, collect a List of Subcontract items belonging to
this Vetting Sheet, and, based on the BQREF, either:
- add the items that don't
aready exist, and give them a status of 'A' (Added)
- check the current details
in the List with any item already existing in this
Vetting sheet, and either:
- update the details if not
the same, and give it a status of 'U' (Updated)
- leave the details of
matching items intact, and give them a status of 'C'
(current)
- modify
the 'status' of this Vetting Sheet as 'updated', 'altered',
and 'not Finalized'. The significance of these flags will be
explained further as we progress through these instructions.
If a
Resource vetting sheet:
- a list of all resources used in the project together with
their aggregated quantities is generated
- the quantity for each resource in this sheet is then updated
from this list
If we make changes to the
Estimate Sections or their workup sheets at any time, all existing
Vetting Sheets will have their 'status' changed to 'not updated',
'altered', and 'not Finalized'. The significance of this will be
explained later.
9. Print the Subcontract Bills of
Quotations
When you are satisfied
that a Subcontract's Vetting Sheet contains the appropriate items
to be quoted, you can now 'print the Subcontract Bills of
Quotations'.
- Click the
'Print' option in the Vetting TAB
- Click the
'Subcontract BQ's' option
- Select the
Subcontracts to Print using the FROM and TO combo box lists
- Click 'Preview'
or 'Print'
NOTE:
If the 'status' of any
Subcontract is 'not updated', then it will not be printed and a
warning given. You will then be required to edit the
Subcontract(s) in question and execute the 'Update' option, review
the results, and then execute the Print option again.
Remember, every time you
alter any data in the base estimate the status for every
Vetting Sheet is reset to 'not updated', 'altered', and 'not
finalized'.
10.
Enter the Subcontract Quotations Received
Generally
The Vetting Sheet by
default has facility initially for four Subcontract quotes,
however these can be expanded to up to 10 per sheet.
Initially these 10
Subcontractors are given the name 'Subby #n', where n=1 to 10. As
subcontractors are invited to Tender, their details are registered
to this sheet.
As the quotations from the
Subcontractors are received, these are entered into the Vetting
Sheet by either entering their rate or cost for each item, or
entering their quotation as a Lump Sum and spreading it
over the items they have quoted on.
Registering a
Subcontractor
You register a
Subcontractor to a Vetting Sheet by:
- Opening the Subcontract Vetting Sheet
you require him to quote on
- Click the 'Vetting->Edit S/C' button
- Click the left or right arrows at the
top to choose his position
- Enter his details
The Email field will be used in the future for automatically
Emailing him the Bills of Quotations
The Address field will be used in the future for automatically
mailing him the Bills of Quotations
- Enter his Quotation
- Enter the '%Discount'
This is not mandatory, but may be useful if you from experience,
are normally able to negotiate a negative discount on his
quotation if accepted, or it may be a positive discount for
Subcontractors who from experience are difficult with variation
claims
Entering a
Subcontractor's Quotation - if supplied as Item Costs or Lump
Sum Quotation
If the Subcontractor has
supplied his quotation as Rates and/or Costs for each item, then
- choose his designated set of columns
(RATEn, COSTn, TAGn)
- against each of the items he has quoted
on enter his Rate or Cost
If the Subcontractor has
provided a Lump Sum quotation only, then
- choose his designated set of columns
(RATEn, COSTn, TAGn)
- in the COSTn column, select the cell
against each of the items he has quoted on
- click the 'Quoted Cost' button (this is
located just below the Options Panel) and then the appropriate
basis of pro-rata from the following popup menu:

- the
Program will
- 'TAG' each selected item with
'Q0' if you selected 'prorata Bill Costs' or 'Qn' if you
selected 'prorata Selected S/C',
- Pro-rata his quotation
against the reference values in the column you selected above,
- and place this in the COSTn
column
If the Subcontractor has
not priced all the items, then you will need to add in a price for
these items using either
- your Estimated Cost
- another Subcontractor's price
- or a manual entry
These are detailed in the following notes
NOTE: The
'%Discount' field entered in the Subcontractor's details
(register) is only used in the case of a Lump Sum Quotation being
used.
Entering a
Subcontractor's Quotation as 'Estimated Costs'
In most circumstances, a
Subcontractor's quotation will exclude certain items. As a fair
and meaningful comparison between the various Subcontractor's
quotes, all items need to be priced.
A formal way of achieving
this is to 'TAG' the unpriced items with your Estimated Cost.
This is achieved by:
- in the COSTn column, select the cell
against each of the items he hasn't included
- click the 'Est'd Cost' button
- the
Program will 'TAG' each selected item with 'E', and using your
Estimated Cost from the COST column as the reference
value, place this in the COSTn column
These 'TAG'ging processes
provide a way for the program to automatically modify the quoted
values when subsequent adjustments are made
e.g. Altering the
Quotation for a Subby as a Lump Sum
Entering a
Subcontractor's Quotation with another Subcontractors Quote
In most circumstances, a
Subcontractor's quotation will exclude certain items. As a fair
and meaningful comparison between the various Subcontractor's
quotes, all items need to be priced.
Another formal way of
achieving this is to 'TAG' the unpriced items with another
Subcontractor's price.
This is achieved by:
- in the COSTn column, select the cell
against each of the items he hasn't included
- click the 'Subby Quote' button
- choose which subby NUMBER you want to
use as the source of the item costs
- the
Program will 'TAG' each selected item with 'Sn', and using the
Cost from the COST column of the designated Subby as the
reference value, place this in the COSTn column
These 'TAG'ging processes
provide a way for the program to automatically modify the quoted
values when subsequent adjustments are made
e.g. Altering the
Quotation for a Subby as a Lump Sum
Selecting the Items to
be TAGGED
As mentioned earlier,
before you can REGISTER TAGS to an item, you must select the items
to be TAGGED. This means selecting (ranging/highlighting) the
cells IN THE COST column of the items to be TAGGED.
This can be done by
either:
- moving to the first cell in the COSTn
column, then while holding down the SHIFT key, pressing the
down/up arrow key
This will provide a contiguous selection of items
- clicking in the first cell in
the COSTn column, then while holding the mouse button down,
dragging up/down until the desired items have been selected,
then releasing the mouse button
This will provide a contiguous selection of items
- While
holding down the CTRL key (Windows) or the COMMAND key
(Macintosh), click in the COSTn column on the cell for the item
to be selected, then while still holding down the CTRL/COMMAND
key, clicking in the COSTn column on the next cell of the next
item to be selected, then repeating this process until all
desired items have been selected
This will provide a non-contiguous selection of items
9. Nominate which
Subcontractor(s) is 'Accepted'
Select the items which you
want to 'Accept' from the desired Subcontractor - you can accept
all or some of a Subcontractor's quoted items, and you can accept
items from more than 1 Subcontractor.
Once the items have been
selected, click the 'Mark as Accepted' button.
The program will then add
the 'A' TAG to the end of any existing TAGs for the selected
items, and update the values in the 'ACCEPTED' column. It is the
value in the 'ACCEPTED' which will be used in the various TENDER
reports in lieu of your Estimated cost.
10.
Transfer the 'Accepted' Quotations back to the Estimate
When you have finalized ALL Vetting Sheets
with the ACCEPTED values, you MUST TRANSFER THE ACCEPTED
VALUES BACK INTO THE ESTIMATE.
Click the
'Vetting->Transfer' button in the Project Window, and the
program will:
- Create a collection of BQREF's
and their aggregated ACCEPTED cost from all the Vetting Sheets
- Open each Estimate Worksheet in turn
and
- Add a VETADJ column into the
worksheet if not already there
- Initialize the value in this
column 0
- Extract from the collection
the value of any matching BQREF's in this
worksheet and place this in the VETADJ column
- Mark the matching BQREF's in
the collection as used
- register an error in the
report list (shown at the end of this process) if a matching
BQREF exists, but it has already been used
- Register an error in the report list of
any BQREF's existing in the collection but NOT used
- Display the error report if errors were
encountered
10.
Print the Reports
There are two sets of
Reports:
- Reports generated from the 'Vetting'
TAB in the Project Print Options dialog
These reports are specific Vetting type reports
- Reports from the 'General' TAB in the
Project Print Options dialog
These reports are the normal Reports which include an option to
'Include Vetted Costs'. This option then simply causes the
program to use the VETAMT for that item in lieu of your
estimated COST.
Do's and Dont's
- Don't
Add columns to the Vetting Sheets (other than with the 'Add
S/C button)
Delete columns from the Vetting Sheets
Rename or modify the Formula for any 'COSTn', 'RATEn', 'TAGn'
columns.
These columns are reserved for the proper functioning and
maintenance of each Subcontract.
- Do
Add additional Subcontractors using the 'Vetting->Add
S/C' button. This guarantees the proper maintenance of the
critical Subcontract columns and their functionality.
The TUTORIAL
Generally
The
following is a TUTORIAL on how to get started using the VETTING
System in EstimatorVJ. It is assumed that you already are
experienced in constructing an Estimate in EstimatorVJ. If you
are not, then you need to go through the standard Tutorial first, and become proficient
in using EstimatorVJ.
We have provided a small
Project to work with - 'A Vetting Example' - initialized with
some data in the 'Concrete' section o illustrate the concepts
and steps you will need to take to use the Vettting system
properly.
This Tutorial will follow
a step by step format, each step starting with the Theory,
followed by the Practical instructions. The Practical
instructions will be shown in a BOLD/ITALICIZED/UNDERLINED font.
About the Project
The Project 'A Vetting
Example' is provided with the Program and simply contains a few
Insitu and Precast items in the 'Concrete' section.
These items are sufficient
to demonstrate practically all of the concepts you will need to
learn to accomplish a successful Tender submission on a Project
which incorporates a mixture of items priced from first
princoples (using Resources) and items priced from Subcontractor
Quotations.
The Procedure
1.
Coding the Estimate with the Subcontract Codes
Open
the Project 'A Vetting Example', then open the Estimate
Section 'Concrete'.
The items in this Section were provided by the
Quantity Surveyor.
For this Tutorial, we will assume that we will be getting
Subcontract Quotes for the INSITU and PRECAST items from
different Subbies, so we will need to REGISTER these two Subcontracts.
2.
Registering the Subcontracts
We do this by clicking the option "Vetting->S/C List"
, and then typing into the SCDE column a UNIQUE code, and the
subcontract title in the Subcontract Name column.
The two subcontracts have already been registered for
you.
Press
the 'ESC' key to close the S/C List (Registry), and
return to the 'Concrete' section.
3. Preparing the Bill for
Subcontract Coding
One condition that is absolute
in a Vetted Project - every
item that is to be vetted must have a BQREF unique to the
Project.
e.g. if
an item to be vetted has a BQREF of '1', then no other item in this
Project, whether it be an item to be vetted or not, can also
have a BQREF of '1'.
If the items are not already
BQREF'd, then use the Autonumber
function in EstimatorVJ to
do so as follows:
- click the heading 'BQREF' -
this will highlight all the cells in the BQREF column
- click on the 'Edit->Autonumber'
button
Done!
4.
Subcontract Coding the Bill
We
are now ready to specify the Subcontracts which apply to each
item, and do this by placing in the SCDE column, the
Subcontract code or codes (separated by a space) which represent
the Subcontractor(s) who will be providing a quotation for each
of the items.
If an
item involves more than 1 Subcontract, then you can either:
- Create a Rate or Cost workup
sheet
- do
not SCDE code the line containing the workup sheet as
if you do it will ignore the workup sheet details and use
that code instead
- enter
an item for each Subcontract required, specifying a valid
SCDE code in the SCDE column. A BQREF is not required at
this level, as this is specified at the Estimate Section
worksheet level
- you can, but it is not
mandatory, enter your estimate of cost for that
Subcontract for this item
- an entry will be added to
the corresponding Vetting Sheet for each item
- Enter the multiple SCDE
codes, one for each Subcontract and separated by the SPACE
character
- e.g. 'COSU COPL REFR'
- an entry will be added to
each Vetting Sheet for each SCDE code
- the COST amount in the
Vetting Sheet will be the COST of this client item divided
by the number of codes
- If you do not want an item to be quoted on, then
leave the SCDE column blank.
- Items do not have to be priced; they can be priced in
the Vetting Sheet if you wish.
- Multiple code any preamble items or headings that you
wish to be included in each of the Subcontract Vetting
Sheets
The items in the CONCRETE
Section have already been coded as an example. Take notice
especially the last item which has been multiple coded by
creating a Rate Workup sheet and entering the Subcontracts
required in there.
The next step in the Vetting process is to CREATE the Vetting
Sheets for each of the Subcontracts. In this example, the
'Insitu' and 'Precast' Concrete.
5.
Creating the Vetting Sheets
This step involves opening up each of the Subcontract Vetting
sheets, initially blank, then populating them (Updating) with the
appropriately coded items in the estimate .
- Click the
'Vetting->Edit VS' option while in the Estimate Section
OR
Click the 'Vetting->Edit' options while at the Project
Window
- Select
the Sheet to edit from the list, in this case 'COINS'
Initially this sheet will be blank
- Now
click the 'Update' button
The program now creates a list of all items in the Estimate
with an SCDE code of 'COINS', and imports this list into
this worksheet
- Press
the 'ESC' key to exit the sheet
- Done
6.
Print a Subcontract Bill
of Quantities
This
report can be sent off to each of the Subcontractors who have
been invited to quote on each of the Subcontracts.
It
lists out each of the items in the selected vetting sheets, with
their BQREF, Description, Unit, and Quantity included, but no
other information, so it can be printed at any time, even though
other contractor's or your estimates have been entered.
Click
the 'Vetting->Print' button in the Project Window, select
the FROM and TO Subcontracts to be included, then click the
'Print' button.
7. Entering a Subcontractor's
Quotations as a Lump Sum
When we have Priced the Base
Estimate
We are now going to edit the 'COINS'
subcontract, and enter the FIRST
subcontractor's quotation as a lump sum.
- In
the Project Window, click the 'Vetting->Edit' button
and select the 'COINS' subcontract from the list
- click
the 'Edit S/C' button
This displays the Subcontractor details dialog.
Initially it will show the details for Subcontractor
#1 (by default set to 'My Est.')
- Use the left and right arrows at the top to
select which subcontractor (1 to 10) you want to
enter/edit the details for.
- Select
#1
- Enter
the details for 'Name' through to 'Ph No.' - the
'Status' field is for future use
- Enter
'10,000' for his 'Quotation'
- Enter
'-10' for the '%Discount', and the 'Val....'
and 'Discounted....' fields will be calculated
This field allows you to increase/decrease the quotation
by % to reflect whether an asset or liability
during the period of the Contract
- Click
'Done'
- click
the 'COST1' heading to select all items in this
column
- click
the 'Quoted Cost' 'Tag' button sitting just below
the Options Panel, and select 'Bill Items' from the
popup menu
This causes the program to pro-rata distribute the
discounted quotation (entered previously as the
subcontractor details) using the estimated 'COST' in the
Bill as the refrence values.
In this case, because we only have two items costed, all
the quotation is attributed to those items only
You will also notice that is has placed the 'Q0' tag in
the TAG1 column designating that these items are to be
costed by prorata application of the discounted
quotation against the costs in the 'COST' column.
When the Base Estimate
has not been priced
The above is the standard procedure when we have priced
the items in the base Estimate, since when the update of the
vetting sheet is activated, the items that come in will have
their rates and costs carried in as well. Thus when we
distribute the subcontractor's quote, there will be meaningful
data to prorata with.
Let's now look at the example where we have predominantly NOT
priced our base Estimate, but simply S/C coded our Bill of
Quantities. This is useful in getting a Subcontract Bill of
Quantities off to the Subcontractors as fast as possible to
get keener quotations or in short Tender periods.
Essentially we start the process the same way:
Select the Edit vetting sheet option
Edit the S/C details
Since we are already in the Vetting Sheet we want to be in, we
continue such by first cleaning up what we previously entered
- Click the
heading in the COST1 column and click the 'Tag->Clear
TAGs' button
- Press
the 'Delete' key to clear the entries
We will now RATE the items while in this vetting sheet so
as to form a basis for distributing Lump Sum Quotations from
our Subcontractors
- enter
a RATE of 10.00 for each of the items CO/2 to CO/4 in
the RATE1 column, and a COST of 11,000 for CO/13
The program will calculate and display the resultant cost
- edit the
Subcontract details for 'Subby #2', and enter his
quotation of say 19,800, then return back to this vetting
sheet
- click on
the heading 'COST2'
- click the
option 'Tag->Quoted Cost' and select menu option
'Selected S/C'
- select
Subcontractor #1
The program will now add the tag 'Q1', and calculate and
display the distribution accordingly.
8. Entering a
Subcontractor's Quotations as Rated/Costed Items
Lets now look at the situation where the THIRD
Subcontractor has supplied his quotation as a 'Rated Bill'.
- click
the 'Vetting->Edit S/C' button
- click
the right arow to select subcontractor #3
- Enter
the subcontractor's name and details
- no need to enter a quotation as he has RATED the
items
- click
'Done' to end editing of the details
- now enter
a rate of 9.00 for each of the items in the RATE3 column
Just like in the base program, you must enter the rate
adjacent the quantity, and as you enter these, the cost will
be calculated and displayed.
There is no need to TAG these items as they are a direct
entry.
If a subcontractor has not
supplied a quotation for all of the items, we have the
following alternatives for the unrated items
- use another subcontractors rates
- use the estimated cost as the rate
- enter our own rate (trivial and not discussed any
further)
Let's apply each of these to the item CO/3 for
subcontractor #2.
- select
the cell in the COST2 column adjacent the item
CO/3
- click
the button 'Tag->Subby Quote'
A dialog will appear requiring you to select which
subcontractor (by number) to use as the source of the
rate. As you select each number, the Name you entered into
their details will be shown below
- Select
subcontractor #1 and click 'OK'
The program will now TAG the item with 'S1' (Subby 1), and
enter the rate from Subby #1 for that item. It will also
redistribute this subbies quote over the remainder of the
items
- Now click the button 'Tag->Est'd
Cost'
The program will now TAG the item with 'E' (Estimated
Cost), and enter the rate from the 'COST' column for that
item
The principle purpose of these special TAG's is to
provide a means for the program to adjust the Subcontractor
rates and Costs should any of the details be amended or
updated later.
9. Nominate which
Subcontractor(s) is 'Accepted'
This aggregated 'Accepted' cost of each item is used to
'adjust' the COST in the base estimate to reflect the
subcontractor quotations. In other words, the program at the
approriate moment, will add up all the subcontractor costs
TAGGED as A(ccepted), and place the sum in the 'Accepted'
column. The difference between the 'Accepted' and estimated
'Cost' is transferred back into the base estimate and placed
in the 'VETADJ' column.
Consequently, it is MOST
IMPORTANT to mark as 'Accepted' ALL the appropriate items.
There are Reports you can print to highlight this, and will be
discussed later.
In our example, let us assume we are going to ACCEPT the
quotations provided by Subcontractor #2.
- Click
the heading COST2 to select all the items
- Click
the 'Tag->Mark as Accepted' button
The program will assign the 'A' TAG to the end of each TAG
already existing, and recalculate and display the
'ACCEPTED' value
10.
Finalizing the Vetting Sheets
Various operations in the Vetted Project depend on the fact
that all the Vetting Sheets
must be 'Finalized' for the operation to complete
e.g.
- 'Transfer' the 'Accepted' costs back into the base
Estimate
- All Project->Reports selected at the Project
Window with the 'Use Vetted Costs' ticked
- Most of the Vetting->Reports
Registering each of the Vetting Sheets as 'Finalized', is
the way the program knows that you have completed and are
satisfied with the data in each of the Vetting Sheets.
Some important concepts and
considerations for you to know:
- every time you edit an Estimate Section, the
program will mark every existing Vetting Sheet as 'not
updated' and 'not finalized'
- every time you edit a vetting sheet, it is marked
as 'altered' and 'not finalized'
- a vetting sheet cannot be 'finalized' if it is
marked as 'not updated'
- the status of a vetting sheet with respect to
finalization, is reflected by the colour of the Finalized
button - red means it is not, and green means it is.
- the RATE and COST columns in the Vetting Sheets
have been made 'protected'
This means that these columns cannot been altered unless
the 'protect' flag is turned off.
DO NOT ALTER THE DATA IN
THESE COLUMNS - IF YOU DO THE 'TRANSFER' PROCESS BACK TO
THE ESTIMATE WILL BE PREJUDICED AND MAY NOT WORK
CORRECTLY
You mark
the status of the vetting sheet as 'Finalized' by clicking
the 'Finalize' button when it is RED. If the vetting
sheet is 'up to date' (that is has been 'Updated' since the
last alteration to any of the Estimate Sections), the
finalized status will be set to 'true' (GREEN), if not then it
will be set to 'false' (RED).
11.
Transferring the Accepted Quotations back into the Estimate
As discussed previously, when ALL vetting sheets have been
marked as finalized, the program will transfer the 'Accepted'
values in the vetting sheets back into the Estimate Sections
and into the column 'VETADJ' adjacent to the pertinent BQREF
item. The value it places in the VETADJ column will be the
difference between the estimated cost and the accepted cost in
the vetting sheet for that item.
This option is started by:
- exiting any vetting sheets you are currently
editing
- click the option 'Vetting->Transfer' at the
Project Window
END OF TUTORIAL